BSR – TA4 DCS Upgrade

Project Name:

FCP270 to FCP280 Migration for Dung Quat Polypropylene (Turnaround 4)

Project Duration:

Start date: 24th, Dec 2019
Finished date: 30th, Sep 2020

Project Scope:

Enersev was responsible for upgrading all the systems DCS/ESD/FGS with the latest proven and approved commercial off Shelf (COTS) hardware and software including:

  • Site survey, design, detail engineering, risk mitigation plans, all the change-over design and OEM document supply,
  • Supply hardware and software
  • Hardware installation, software configuration & upgrade, testing, troubleshooting, commissioning, and handover
  • Support start up
  • Training for operators and engineers

Goals:

  • To upgrade the existing Foxboro DCS FCP270 to FCP280
  • The existing workstation Windows operator system will be replaced with the latest Windows 10 and Server 2016
  • To keep system security, reliability, and performance, risks under control due to the withdrawal of support for older releases of FCP 270

Results:

  • Successfully upgraded FCP 270 to FCP 280 Controller: Total 8 Pairs
  • Successfully upgraded DCS Workstation/Server Operating System from Windows 7 to Windows 10, and Windows Server 2008 to Windows Server 2016:
  • Successfully upgraded Tristation 1131 software to Version 5.0 for the ESD/FGS System
  • During Plant starting up, all system was running smoothly and effectively